Consumption of treated water
Maejo University has a 75,000-cubic meter raw water pond that supplies water for water supply Plant 1; a 20,000-cubic meter pond that provides water for water supply 2; a 32,200-cubic meter pond that supplies water for water supply Plant3; a 60,000-cubic meter pond that is used for agricultural purposes. All together, the total amount of surface water is 187,200 cubic meter. Meanwhile, Maejo University uses building water supply for 719,604 cubic meter in this year.
The percentage of treated water consumed from water system treatment compared to all water sources was 46.04 %, as shown in the equation below. The treated water of Maejo University between October 2020to September 2021has a total volume of 417,4544 m3. All treated water were supply into pipe line to the 12 points of treated wastewater release throughout the universityarea for utilization.